msse-ai-engineering / synthetic_policies /change_management_process.md
Seth McKnight
Add new policies and guidelines for various operational areas (#9)
2d593b8
|
raw
history blame
3.07 kB
# OPS-SOP-019: Change Management Process
**Effective Date:** 2025-08-01
**Revision:** 1.1
**Owner:** Project Management Office (PMO)
## 1. Purpose
This Standard Operating Procedure (SOP) establishes a formal process for requesting, evaluating, approving, and implementing changes to a project's scope, timeline, or budget. The objective is to control "scope creep" and ensure that any changes are properly assessed and approved before being acted upon.
## 2. When to Use This Process
This process must be initiated when a change is proposed that affects any of the "triple constraints" of a project:
- **Scope:** Adding or removing features, deliverables, or requirements.
- **Timeline:** Any change that could impact a major milestone or the final delivery date.
- **Budget:** Any change that results in an increase or decrease in the approved project budget.
## 3. The Change Management Steps
### Step 1: Submission of Change Request
- **Who:** Any project stakeholder can propose a change.
- **How:** A formal **Change Request (CR)** must be submitted using the designated Jira ticket type.
- **Content:** The CR must include:
- A clear description of the proposed change.
- The business justification (the "why").
- The perceived benefits and risks of implementing the change.
### Step 2: Impact Analysis
- **Who:** The Project Manager (PM) is responsible for leading the analysis.
- **How:** The PM works with the project team to assess the impact of the change on scope, timeline, budget, and resources.
- **Output:** The PM documents the findings of the impact analysis directly in the CR Jira ticket. This must be a quantitative assessment (e.g., "This will add 80 hours of development work and delay the UAT phase by 3 days").
### Step 3: Approval by the Change Control Board (CCB)
- A Change Control Board (CCB) is established for each project. The CCB's composition is defined in the Project Charter, but typically includes the Project Sponsor, PM, and key technical/business leads.
- The PM presents the CR and the impact analysis to the CCB.
- The CCB makes one of three decisions:
- **Approved:** The change is accepted.
- **Rejected:** The change is not accepted.
- **Deferred:** The change may be considered at a later date.
### Step 4: Implementation & Communication
- If the CR is approved, the PM is responsible for:
- Updating the project plan, budget, and other relevant documentation.
- Communicating the approved change to all project stakeholders.
- Integrating the new work into the project's backlog and schedule.
## 4. Emergency Changes
In rare cases where a change is required to fix a critical issue, an expedited process may be followed with verbal approval from the Project Sponsor, but a formal CR must be submitted retroactively within 48 hours.
## 5. Related Policies
- **Project Kickoff Procedure (OPS-SOP-018)**
## 6. Revision History
- **v1.1 (2025-10-20):** Clarified the role of the Change Control Board (CCB) and added a section on emergency changes.
- **v1.0 (2025-08-01):** Initial version.